Select Page

New Fire Hall

Late 2025 saw the opening of a new Salisbury Fire Rescue Facility, built with the intention to adequately serve the needs of the Town’s volunteer fire department and ensure the department has adequate space and resources to continue providing an exceptional level of service for residents. It is located at 3105 Main St. in Salisbury.

This web page provided regular updates for residents as this Town construction project progressed.

Project Update (November 8, 2025):

The Town hosted a Grand Opening/Open House on Saturday, November 8 from 10:00 AM-2:00 PM. This included a ribbon-cutting and greetings from invited guests at 11:00 AM. Throughout the day, tours were offered. The event also featured a free BBQ. The Office of the Fire Marshall fire simulators were also on-site.

FAQs:

How has this project been progressing?

Project Updates

October 16, 2025:

  • Town Council called the debenture for the Federation of Canadian Municipalities (FCM) and the Municipal Finance Corporation (MFC) on October 6, 2025. Occupancy is expected to begin on October 20. Final deficiency inspections were undertaken today (Oct. 16). The Town is hosting a Grand Opening/Open House on Saturday, November 8 from 10:00 AM-2:00 PM. The public is invited and is welcome to attend! This will include a ribbon-cutting and greetings from invited guests at 11:00 AM. Throughout the day, tours will be offered. Following greetings and ribbon cutting (that starts at 11:00 AM), a free BBQ will be available. The Office of the Fire Marshall fire simulators will also be on-site. The Town and the Volunteer Department look forward to welcoming you to the new space!

September 24, 2025:

  • The exterior signage on front of building was installed on September 23. Fire Marshall inspections have been completed. Substantial completion on the full project, for purposes of provincial legislation and construction liens/holdbacks, was declared on September 22, 2025. Work remains ongoing for addressing final deficiencies and arranging owner training. Final items such as deep construction cleaning, furniture assembly, keying, etc. are ongoing, as is final commissioning (testing) of all systems.

August 28, 2025:

  • Concrete is being prepped for completion both at the front and the back of the building. Asphalt fine grading begins early September with asphalt being laid the following days. Furniture for interior has been ordered and is expected to arrive in coming days.

August 1, 2025:

  • The initial interior architectural inspection for substantial completion has been undertaken. The Town’s contractor will begin working on the deficiencies. On the exterior, the concrete apron has begun being poured (one half complete) and curb has also been installed. Landscaping and exterior work will continue in the coming weeks. The project remains ahead of schedule.
  •  

July 17, 2025:

  • The overall project remains on track or ahead of schedule. Rebar is being installed for the concrete apron this week, and curb installation is expected next week, at which point the concrete apron can be poured. The interior of the building is nearly entirely complete, with architectural inspections being undertaken this month. Commissioning of systems has begun, and is expected to be completed early August. Into August, work will focus on the exterior items such as landscaping, final touches on the exterior masonry (concrete bricks), finalized site preparations and commencing Owner training on the facility and it’s systems.

May 5, 2025:

  •    
  • As of early May, all flooring is completed on both levels with the exception of certain areas. Painting is completed in most offices. Drywall and trusscore installation is continuing in the apparatus bay. The majority of roofing is complete, with the exception of areas that will not be installed until the concrete masonry is installed. Work on the interior is ahead of schedule.

April 10, 2025:

  • In the coming weeks, roofing will continue on the exterior. On the inside, fixtures/devices/diffusers in the T-Bar ceilings are approximately 85% complete. Ceramic tiling in applicable walls are complete, with floor tiling well underway. Painting has occurred in several interior offices. The building is expected to be energized with permanent power by month-end. In the apparatus bay, work continues on the hose tower with the final roof piece for the building having been placed this week and strapping continues on the apparatus bay walls in addition to final touches on the trusses. In the coming weeks, geothermal lines will be filled with water/glycol, the apparatus bay stairs will be enclosed, and doors and hardware will begin installation. Work remains on schedule, with the interior of the building expected to be completed by Summer and the remaining site work on the exterior and building masonry expected to be completed by Fall.

March 17, 2025:

  • Work has shifted to interior finishes on the building, the area of focus for the coming weeks. All roof portions have been lifted and placed. The hose tower ICF will be poured, in two sections, in the coming weeks. On the inside, drywalling is complete and crews have painted or continue painting. Tiling has begun in washrooms.  Several mechanical and electrical rough-ins have been completed, and the t-bar ceiling is being installed. The project remains on-schedule.

February 7, 2025:

  • In recent weeks, all interior framing has been complete. The apparatus bay trusses are expected to be lifted via crane in the coming weeks. The bottom-level work is at the point of receiving in-wall inspections from the Town’s design team and drywalling will continue, as well as mechanical and electrical rough-ins. The metal roofing is ongoing, with the majority to be completed in the coming weeks, except for sections where masonry work will be required in the Spring. The project remains on schedule, although weather delays prior to the Holidays have reduced the amount of flexibility in the project schedule.

December 23, 2024:

  •  

November 7, 2024:

  • Concrete has been poured in both the office area and the apparatus bay. Forming for the interior of the offices has been complete as of November 6. The exterior walls of the apparatus bay will have concrete poured in the next week, in addition to erecting the steel for the roof the same week. Trusses are expected to arrive in early December. The project remains on schedule to be enclosed by Christmas, ensuring a continuation of the schedule throughout the Winter.
    SFR Station Video

September 24, 2024:

  • The concrete form work is well-underway, as is civil work on-site (ie: drainage, sewer connections, etc.). All geothermal wells and the domestic well have been completed. Work in the coming weeks and months will prioritize having the building weather-tight by the Holidays in order to begin work on the interior come the new year.
  •    

August 2, 2024:

  • The Design Team and General Contractor continue to finalize logistics such as sub-contract awards, shop drawing approvals, etc. The Town has received the building permit for the Facility. Work is expected to begin with foundation and footings in the coming weeks.
  •  

May 28, 2024:

  • During a Special Council Meeting on May 27, 2024, the Town awarded the tender for the construction of the facility to Maxim Construction Inc. This followed the closing of the bids which received five submissions, with the successful proponent being the lowest bidder.
  • In the coming weeks, the Town will formally negotiate a contract with the lowest bidder and will begin formalizing a construction schedule. Pursuant to the tender specifications, the Town continues to anticipate occupying the facility by Fall of 2025.

April 8, 2024:

  • The Town has issued the tender for the construction of the Facility on NBON (New Brunswick Opportunities Network). The deadline is May 16th at 2pm.

November 3, 2023:

  • The Town’s contractors are analyzing land survey data and continue to work on construction documents, as well as a tender package, in anticipation of tendering the project in the Spring of 2024.
  • The site has been cleared and conceptual design and schematic design have been completed.
Why does the Town need a new Fire Hall?

In the 2023-2026 Town of Salisbury Strategic Plan, Town Council committed to moving forward on a new Fire Hall for the Salisbury Fire Rescue Department.

There are a number of reasons the Town decided to pursue a new station, which include:

  • A lack of space in the current fire hall, including inadequate space for members to dress/undress, remove or load equipment into the fire apparatus, a limited number of members due to space constraints, a limit of 12 parking spaces adjacent to the Station, etc.;
  • The current Fire Hall is immediately across from Salisbury Regional School, presenting significant issues related to parked vehicles that interfere with fire trucks leaving/entering the station;
  • Limited space for apparatus parking, meaning trucks are “double stacked”, preventing the second vehicle from leaving in the event of a malfunction with the front vehicle;
  • Limited dedicated space for the Department for call debriefs, training, and meetings;
  • Until recently, there was no on-site washing or drying facilities for turnout gear. While a temporary solution has been included in the current station, this removed shower facilities from the building.
Where is the current Fire Hall?

The current fire station is part of the municipal building on Douglas Street in Salisbury. The original fire station was constructed in 1975 as a standalone structure (48 years ago), with the subsequent addition, including municipal offices, in later years.

How busy is the Salisbury Fire Rescue Department?

Salisbury’s Fire Department is composed of dedicated volunteers. In 2022, the Department responded to 202 calls. While the Department responds to traditional fire calls (structure fires, vehicle fires, grass/brush fires, etc.), in 2022, this only represented 19% of their calls. The Department also responds to medical calls (13% of calls in 2022), motor vehicle accidents (MVAs) (41%), alarm calls, requests to assist other fire departments, and more.

As of mid-September, 2023, the Department has responded to 128 calls. It is projected to be nearly 170 by year-end.

In addition to calls, the Department trains every Monday night to ensure that they can be prepared to answer the call(s) of Salisbury residents.

How big is the new building?

The total building footprint is approximately 12,460 square feet. This includes the apparatus bay, station area, and the mezzanine (which is 2,900 square feet).

When is it expected to be completed?

As of May 2024, a contract for construction has been awarded. Throughout design, the Town anticipated occupying the facility by the Fall of 2025. As of early 2025, the project remains on schedule, just past 50% completion.

What will the new Station look like?

The Town is currently anticipating that the building will have a brick exterior. The latest conceptual renderings can be seen here:

What is in the new building?

The following is an overview of the building features:

  • Double-entrance double apparatus bay;
  • Multi-purpose room, accessible to the Public;
  • Gym, available to Department members and municipal staff;
  • Lounge area;
  • Male and female washrooms, specific to the Department (separate from space accessible to the public);
  • A breathing apparatus room;
  • Mechanical/compressor room;
  • A workroom;
  • A radio room;
  • One office (Fire Chief);
  • A flex office, accessible to Department members who may choose to work remotely from the station and increase availability of members during the day-time hours;
  • A gear-cleaning room;
  • Storage/mezzanine, with option for future use, on a second floor.

The following presents an overview of the final floor plan:

Who designed this building?

In early 2023, the Town issued a Request for Proposals (RFP) for professional services for the design of the Salisbury Fire Rescue Facility and received six (6) proposals. The Town retained Jost+ Architects for this work, and has been working with them since the award for the building design. While Jost+ Architects is the primary consultant, they have sub-contracted engineering work to Fundy Engineering (mechanical, electrical, civil) and Giffin Engineering (structural).

As part of the design work, the Town struck two primary working groups:

  • A Fire Department Working Group, consisting of the Chief, the Deputy Chief, three Department members, and the Town’s Chief Administrative Officer (CAO);
  • An internal working group consisting of the Chief Administrative Officer (CAO), the Manager of Infrastructure & Public Works, the Clerk/Treasurer, and the Lead Architect.
How will this building be paid for?

This project will be financed with a debenture (loan) through annual installments through the Town’s Operating Budget. The Town requested approval to borrow up to $7,500,000 in November of 2023 through the Municipal Capital Borrowing Board (MCBB) and was approved in the Fall as well. This will finance the project over a 20-year term.

In addition to the debenture, the Town has submitted applications to the Federation of Canadian Municipalities (FCM)’s Green Municipal Building Fund. This fund aims to assist municipalities with financing energy-efficient buildings through a 15% grant and a subsequent low-interest loan (for up to 80% of the project costs). Throughout the project, the Town has compared costing options between traditional borrowing means available to Municipalities and through FCM’s funding program, and has determined that pursuing the FCM option, even if certain environmentally-proactive measures increase construction costs, is the most feasible option for the Town. The Town’s application is in the final stages of FCM’s process and the Town anticipates a response in the coming weeks.

The design costs have been paid for with the Town’s 2023 Operating Budget and with a contribution through the Canada Community Building Fund (CCBF) (approximately $188,000). As well, the Town has applied to FCM’s Feasibility Study stream to fund a portion of the design costs, which was successful, paying for approximately $85,000 of the costs.

What will happen with the existing Fire Hall?

The Town has, in recent years, completed a spatial analysis for municipal buildings. In 2023, it completed an architectural assessment of the building space to ensure that the municipal building at 56 Douglas Street could sustain the growth of the Town in light of Local Governance Reform. This work confirmed that the municipal building will fit the needs of the Town for the foreseeable future. The current Fire Department bays will become the area for the Town’s Department of Infrastructure and Public Works. This will optimize the space, better protect Town assets from vandalism and theft, reduce off-site storage costs, and provide much-needed space for maintenance, repairs, and general workspace.

What has the Town done so far for the new Fire Hall?

The following presents an overview of the work undertaken for the new Facility since 2019:

2019:

  • In 2019, a Needs Assessment was completed for a new Fire Hall.

2022:

  • In 2022, the land transaction for the building location was completed for the land on Main Street.

2023:

  • In 2023, the Town retained the Architect firm to design the Facility and have the 2019 Needs Assessment updated, create the Room Data Sheets (specific requirements for each element of the Facility), and design the building;
  • The Town worked with the Engineering sub-contractors to undertake an Energy Model Report to optimize energy performance;
  • In the Fall, an external cost consultant will complete work to determine potential cost savings and provide a pre-tender cost estimate for the facility;
  • The lot has been cleared for construction, and the Town has undertaken topographical surveys as well as geo-technical surveys to finalize the building location and soil quality prior to preparing a tender package.

2024:

  • The Town completed a geothermal test well and conductivity test on site to verify civil engineering drawings and finalize the projected mechanical requirements for the geo-thermal system;
  • The Town tendered the Facility in April with the project closing in May. It was subsequently awarded during a Special Council Meeting on May 27, 2024.

Additional project updates can be found by consulting the summary update at the top of this page, or, consulting the “How has this project been progressing?” drop-down.

How has the Town considered environmentally-friendly design elements with this building?

Sustainability and environmental performance has been a top priority for the Town in constructing this Facility, recognizing that it is intended to serve the needs of the Town into the future. In fact, the building will be net-zero ready.

The Town worked with the Design Team and their sub-contractors to complete an energy model and energy simulations, identifying the most efficient energy options, primarily related to the heating system within the building. With the latest model completed with the issued for tender drawings, the building reduces anticipated energy consumption for standard construction for this building by over 40% and reduces the annual operating costs by over $20,000. The primary reason for this reduction is the construction of the facility with ICF shell and a geo-thermal heating and cooling system.

The building will also have electrical infrastructure installed, and space on-site, for future solar panels. This will be the catalyst for it to be a building that produces the energy it consumes in a future phase of the project.

Will this building meet the needs of the Department into the future?

The Station has been designed to serve the needs of the Town well into the future. The apparatus bay consists of drive-through double bays. This will more than double the current apparatus bay space available. In addition to this, the Town has provided significant storage and future-use space in a second-floor mezzanine of the Facility. On the land itself, the Town is reserving ample space for future amenities such as detached storage, etc. that may be required into the future.