During the Regular Council Meeting of December 9, 2024, Salisbury Town Council approved the 2025 General Operating and Utility Budgets, maintaining the tax rates amongst all sub-units within the Town boundaries. On December 17, 2024, these budgets received approval from the Province of New Brunswick.
The General Operating Budget for the Town in 2025 is $7,881,268, with the property tax rates remaining unchanged for all sub-units. The Utility (Wastewater) budget is $496,479, with the rate for users set at $400/unit, also unchanged from 2024.
“In 2024, we saw significant progress in our Town: many capital projects, including the start of our new fire hall and the reconstruction of the southern berm of our wastewater polishing pond, progress on residential development projects, and changes to the Town’s operations to reflect Local Governance Reform,” said Mayor Robert Campbell. “As committed to residents in 2024, the increase to the Town’s property tax rate last year was an abnormal occurrence that was required to right-size the municipal budget. With thanks to Council’s diligence on acting on strategic priorities in a fiscally-prudent fashion, and the increasing residential and non-residential tax base growth that reflects the competitiveness of our market and region, we are able to maintain the rate going into 2025 for all sub-units, while continuing to act on strategic priorities and maintain a competitive tax rate.”
In 2024, former Local Service Districts (LSDs) paid 90% of their share of proportionate (shared service) costs. In 2025, this has been reduced to approximately 78%, reflecting Council’s commitment to ensuring that all sub-units pay a fair and reasonable share for access and use of municipal services.
Highlights of the 2025 Operating Budget are as follows:
- Funding for the short-term financing of the Salisbury Fire Rescue Station, including the cost of issuing the debenture in late Fall, pending interest rates and project completion;
- $150,000 to begin the Town’s Residential Development Incentive Program and increase the housing supply in our community;
- Over $650,000 to contribute to the Town’s 2025 Capital Budget, which will include projects such as the construction of a public park space in the Spring Garden subdivision, replacing the culvert at the Reeder Road/Route 106 (Main Street) intersection, and the installation of railings on the railway trestle to increase safety for trail users;
- Increases to all event budgets to continue enhancing event and programming offerings year-round, in addition to increasing the beautification budget for increased holiday lighting at Highland Park.
- The Town will also be participating in a regional waste collection contract with several municipalities in the Southeast, to begin in February of 2025;
The property tax rates for the Municipality are as follows (unchanged from 2024):
| Sub-Unit |
Local Government (Town) Rate (per $100 assessed value) |
NB DTI (Special Provincial Levy) (per $100 assessed value) |
Total Rate (per $100 assessed value) |
| Salisbury (V) | $1.1599 | N/A | $1.1599 |
| Coverdale (LD) | $0.6335 | $0.4115 | $1.0450 |
| Salisbury (LD) | $0.6346 | $0.4115 | $1.0461 |
| Moncton (LD) | $0.6394 | $0.4115 | $1.0509 |
| Elgin Parish (LD) | $0.6388 | $0.4115 | $1.0504 |
The following table provides an overview of the tax bill for different value(s) of properties, for comparison only:
| Assessed Value (for taxation) Comparison | Salisbury (Village) Sub-Unit ($1.1599) | Former Local Service District Sub-Units (average rate, $1.0481) * |
| $200,000 | $2,319.80 | $2,096.20 |
| $250,000 | $2,899.75 | $2,620.25 |
| $300,000 | $3,479.70 | $3,144.30 |
| $400,000 | $4,639.60 | $4,192.40 |
| $450,000 | $5,219.55 | $4,716.45 |
* This rate includes the Special Provincial Levy, which goes directly to the Government of New Brunswick and not to the Town of Salisbury.
In 2025, 1,734 of the properties in the Town of Salisbury are within the provincial spike protection mechanism, meaning their property assessment as determined by Service New Brunswick has increased by more than 10% year-over-year to reflect the real and true value of the real estate market.
During the same meeting, Council approved the 2025 Wastewater Charge for those connected to the Wastewater (Sewer) system under the jurisdiction of the Town (those within former Village of Salisbury limits). The 2025 user rate will remain at $400 per unit.
Salisbury’s 2025 Operating and Wastewater Budgets, which have been approved by the Government of New Brunswick, can be found online HERE.